Product Description
Congratulations on the purchase of the ChemInstruments Adhesion/Release Tester. This versatile, user-friendly, carefully designed instrument allows you to determine adhesion and release values of adhesive laminates at various speeds and at various angles of separation.
The unit has the following features:
- 2 modes of operation: constant speed and ramped speed testing.
- Selectable testing speeds.
- Selectable separation angles from 90 degrees to 180 degrees.
- User-selectable data acquisition area on the test sample.
- Selectable units of measure: Kilograms, Grams, Newtons, Pounds, and Ounces.
- Compatible with EZ-Data System software.
Specifications
| Electrical, 120 model | 104-126 VAC, 50/60 Hz, 3 amps |
|---|---|
| Electrical, 240 model | 208-252 VAC, 50/60 Hz, 3 amps |
| Operating Temperature | 32–150 °F (0–70 °C) |
| Humidity | 0–55% relative humidity |
| Speed | 1-1200 in/min (1 in/min increments) 3-3048 cm/min (1 cm/min increments) |
| Dimensions (W x D x H) | 36 x 13 x 24 in (91 x 33 x 61 cm) |
| Weight | 92 lbs (42 kg) |
Safety Warning
WARNING: This equipment can cause injury if not used properly. It is the operator's responsibility to read and follow all safety instructions.
WARNING: Due to its weight and size, use 2 people to move the AR-2000.
ELECTRICAL WARNING: Ensure the unit is connected to the correct power supply (120 or 240 VAC). Incorrect power may cause equipment damage or electrical hazards.
Unpacking
Carefully unpack the Adhesion/Release Tester and inspect for shipping damage. If damage is found:
- Take photographs
- Retain all packaging
- Notify the carrier immediately
Package Contents Checklist:
- Test frame (with motor/drive and data acquisition system)
- User manual (this document)
- The mast for mounting the load cell assembly
- The pivoting bracket and attached load cell assembly with calibration bracket and wire
- Power cord
Installation Instructions
Carefully remove the test frame, drive assembly, and data-acquisition components from the packaging. Place each component on a sturdy, level benchtop capable of supporting the full weight of the instrument.
Verify that the installation area meets the required physical dimensions outlined in the Specifications section of this manual. As with any precision laboratory device, the AR-2000 should be installed in a controlled environment. For optimal performance and measurement stability, locate the instrument in an area maintained at 72 ± 2°F and 50 ± 5% relative humidity.
Attaching Mast and Load Cell Assembly
Attach the mast to the test frame using the supplied small clamping knobs. Ensure that the mast is oriented correctly, with the flat side positioned toward the back of the unit as shown in Figure 2. The mounting holes for the mast are located on the back panel of the test frame, toward the left side when viewed from the rear.
NOTE: For tests involving shorter sample strips at 90° or 180°, install the mast using the holes labeled “C” in Figure 1. For tests involving longer sample strips, use the holes labeled “B” in Figure 1.
Slide the pivoting bracket with the load cell assembly onto the mast. Position the assembly at the desired height and tighten the large clamping bolt to secure it in place.
One end of the load cell cable will need to be connected to the side of the AR-2000. Connect the other end of this cable to the corresponding socket on the load-cell assembly. Refer to Figure 2 for connector location and orientation.

Attaching Switches
Connect the switch cable assembly to the designated connector on the side panel of the AR-2000. The opposite end of this cable terminates in three white reed switches labeled “Home,” “Start,” and “Stop.” Each reed switch is fitted with a Velcro® fastener designed to attach to the fastener tape located on the back rail of the test frame.
- Attach the reed switch labeled “Home” to the fastener tape at the right end of the test frame.
- Position the “Start” switch approximately 2 inches to the left of the Home switch.
- Attach the “Stop” switch to the fastener tape at a point roughly aligned with the side of the control cabinet.
Refer to Figure 2 for the proper placement of each switch.
These switches define the measurement area for the test sample, so their positions may need to be adjusted. You may need to experiment with different placements to achieve the proper measurement range for your specific samples.
Connecting the Power Cord
WARNING: Make sure the power source matches the requirements of the Adhesion Release Tester. Damage will occur if this unit is plugged into the incorrect power supply. The AR-2000 is NOT a dual voltage machine.
Insert the power cord into the receptacle on the rear panel of the unit, then plug the opposite end into a properly grounded AC outlet (see electrical specifications).
Notice that the on/off power switch is located directly beside the power cord receptacle on the backside of the test frame.

Theory of Operation
Technical Overview of Peel/Release Testing
Test Method
A pressure-sensitive adhesive laminate is peeled at a selected angle (typically 90° or 180°). Peel speed is user-selectable from 1 to 1200 in/min.
Force Measurement
An electronic load cell measures the peel or release force throughout the test. Force data is transmitted to the data acquisition unit for processing.
Reed Switch Positioning
Movable reed switches on the test bed define the measurement zone. Only force data collected between the Start and Stop switch positions is recorded.
Data Sampling & Processing
Load cell sampling rate: 400 samples per second. Every 8 samples are averaged to create one recorded data point. One data point is generated approximately every 20 milliseconds.
Data Storage & Calculations
Up to 10,000 data points can be stored for a single test. Recorded data points are used to calculate maximum force, minimum force and average force.
Key Components
- POWER SWITCH is located on the back panel of the control cabinet directly beside the power cord connection. (See Figure 3)
- FUNCTION SWITCHES control the start and stop of data acquisition. The “Home” switch cycles the data acquisition unit into its “ready” mode. The “Start” switch starts the data acquisition and the “Stop” switch stops the data acquisition. (See Figure 2)
1
2
3
4
- 1MAST holds the pivoting bracket with load cell assembly and permits running tests at angles between 90° and 180°. A small peg on the backside of the mast allows for convenient positioning of the load cell for testing at a 180° angle.
- 2CLUTCH HANDLE engages and disengages the test platform with the drive chain. The clutch handle is disengaged when the handle is to the left. The clutch handle is engaged when the handle is to the right. The clutch handle is disengaged in this photo.
- 3TEST PLATFORM provides a surface to hold the test material.
- 4EDGE BRACKETS hold test panels in place on the test platform.
5
6
7
8
- 5GRIP secures the free end of the test strip to the load cell.
- 6CALIBRATION WIRE is used in the load cell calibration process. It will be removed prior to testing.
- 7CALIBRATION BRACKET is used in the load cell calibration process. It will be removed prior to testing.
- 8LOAD CELL ASSEMBLY consists of the mounting bracket for the load cell with grip. The LOAD CELL measures the forces involved with an Adhesion/Release test.
Touch Screen Format
Main Screen
| Button/Label | Function |
|---|---|
| Current Load | Displays current load cell reading |
| Current Speed | Displays current test speed |
| Start/Stop Motor | Starts/Stops the chain drive system |
| Setup | Access setup options |
| Graph | Shows graph and results from last test |
| Statistics | Displays data from last test |

Setup Screen
| Button | Function |
|---|---|
| Calibrate Load Cell | Load cell calibration |
| Units | Set speed and force units |
| Speed/Ramp/COF | Set constant test speed, ramp, or COF parameters depending on Mode selection |
| Mode | Constant Speed, Ramp Speed, COF |
| Halt Mode | Automatically halts the chain with 5 minutes of inactivity |
| Qualify Operation | Verifies hardware function |
| About | View software and hardware version |
| Exit | Return to main screen |
NOTE: After 30 seconds of inactivity in any setup screen (except Hardware Tools), the screen will return to the Main Screen.

Graph Screen
Displays the following data from the last test:
- Force vs. time graph
- Minimum and maximum values
Statistics Screen
Shows test results, including:
- Minimum and maximum
- Variance and standard deviation
- Work (area under the force-time curve)
Qualify Operation
The Qualify Operation screen is designed to verify the proper functionality of key system components.
Diagnostic Tools
- Current Load: Displays the real-time force measured by the load cell in selected units.
- Verify Load Cell: Records load cell output for 10 seconds. No movement occurs during this test. The system displays a force graph and statistical summary to confirm load cell accuracy using a calibration weight.
- Load Cell Reading: Shows raw analog-to-digital values from the load cell. Pulling on the grip gives values > 32000; pushing on the grip gives values < 32000.
- Switch: Shows the current state of each switch. Drag the cart's magnet past each switch to verify that the display changes to ON and OFF accordingly.

Machine Setup
Power On the Instrument
WARNING: The instrument must operate within a temperature range of 32°F to 122°F (0°C to 50°C).
WARNING: Before applying power, ensure that the equipment is completely free of condensation, both inside and out. Moisture can cause internal damage or malfunction.
Turn on the master power switch located on the back panel of the control cabinet, next to the power-line receptacle. After power is applied, the internal control board will perform an automatic self-test. As a safety measure, the chain drive will remain inactive until the user presses the START MOTOR button on the touchscreen.
Load Cell Calibration
To ensure accurate and reliable test results, it is essential to calibrate the load cell before use. The Adhesion/Release Tester is equipped with an integrated calibration procedure, accessible through the touchscreen interface. Calibration should be performed:
- During initial setup
- After relocation or extended periods of inactivity
- Whenever measurement accuracy is in question
- As part of routine maintenance
IMPORTANT: Power on the Adhesion/Release Tester for at least 30 minutes prior to calibration to allow the system to stabilize.
NOTE: The calibration process uses grams as the default unit. Ensure calibration weights and inputs are in grams.
Calibration Procedure

Follow these steps to calibrate the load cell:
- Move the pivot head assembly containing the load cell assembly to a position approximately 8 inches above the surface of the test frame.
- Confirm that the load cell is mounted at the same angle as the test angle.
- Attach the calibration fixture onto the bottom of the load cell mount using the two small bolts.
- Place the knotted end of the calibration wire in the jaw of the grip taking care to keep the wire in a straight line from the grip to the pulley. Run the wire over the pulley so that a calibration weight can be attached to the end of the wire.
- Select SETUP from the main screen.
- Select CALIBRATE LOAD CELL from the setup screen.
- The first screen in the calibration process describes the 2-point calibration process. Select OK to continue.
- The next screen measures the low calibration value desired (typically 0). Make sure that you do not have a weight hanging from the calibration string and select OK.
- The next screen measures the high calibration value desired. This weight should be close to the maximum expected test value. Hang the weight on the loop end of the calibration wire making sure that the wire is able to move freely.
- Set the high calibration value by selecting CHANGE and entering the value of the weight in grams and select ENTER.
- Make sure that the calibration weight is completely at rest and then select OK.
- The display will show the main screen and the current reading of force will be displayed under CURRENT LOAD.
- Verify the calibration by hanging a different calibration weight on the calibration wire.
- Turn motor on. Engage the test platform to simulate running a test. After the test platform has traveled to the left of the stop switch, confirm that the average measured force is the same as the selected weight hanging from the calibration string.
- Repeat the calibration procedure if necessary.
- Remove calibration bracket and calibration wire when finished with the calibration procedure.
Calibration Troubleshooting
A
B
C
D
- ABe sure that the calibration wire is in the groove running through the center of the bearing.
- BBe sure there is a gap between the load cell sample grip and the load cell housing.
- CBe sure that the load cell cable is attached to the load cell.
- DBe sure that the calibration bracket is attached to the load cell housing.
Grip Operation
To operate the grip:
- Open the grip by turning the thumb screw counter-clockwise.
- Insert the free end of the looped specimen into the grip.
- Close the grip by turning the thumb screw clockwise until secure.
IMPORTANT: The grip connects to the Load Cell Assembly via a mounting pin and yoke. Always remove the grip from the assembly to load test specimens safely.

WARNING: Avoid rotating the yoke on the threaded mounting rod. If the yoke contacts the wall of the load cell housing, permanent damage may occur. Maintain a visible gap between the yoke and the housing to allow the load cell to operate correctly.
Units Setup
To adjust the units of force and speed:
- From the Main Screen, tap Setup.
- Select Units.
- Choose your desired units.
- Tap OK to save your selections.
Mode Setup
The AR-2000 can operate in constant-speed mode, ramp-speed mode, or coefficient of friction (COF) mode.
- From the Main Screen, tap Setup.
- Select Mode.
- Choose appropriate test mode.
- Tap OK to confirm.
Constant Speed Setup
To set the load cell assembly travel speed for your test:
- From the Main Screen, tap Setup.
- Select Speed.
- Enter the desired value, and press Enter.
- Tap OK to confirm.
Ramp Speed Setup
The following procedure describes how to configure the parameters for Ramp Speed Mode.
- Select SETUP from the main screen.
- Select RAMP SETUP from the setup screen.
- Select the box next to each parameter to open the parameter-entry screen. Enter the desired value, then select ENTER or OK to confirm.
Definition of Ramp Parameters
- Start Force: The force that must be detected by the load cell before the ramp sequence begins. While the system is searching for this force, the machine operates at 5 in/min. If Start Force is set to 0, the ramp will begin immediately when the START TEST button is pressed.
- Start Speed: The initial speed for the first step of the ramp test.
- Speed Increment: The amount by which the speed increases at each step of the ramp.
- Time at Each Step: The duration the system will maintain each programmed speed travel.
- Number of Steps: The total number of speed levels that will be executed during the ramp test.

COF Setup
The following procedure outlines how to configure the Coefficient of Friction (COF) Mode parameters.
- Select SETUP from the main screen.
- Select COF SETUP from the setup screen.
- Select the box next to each parameter to open the parameter-entry screen. Enter the desired value, then select ENTER or OK to confirm.
Definition of COF Parameters
- Speed: COF testing can be performed at speeds from 1-24 inches/minute or 3-60 centimeters/minute.
- Sled Mass: The allowable sled mass range is 1-2000 grams.
- Static Length: The duration used to measure static friction. The adjustable range is 1-10 seconds.
A test sled is required to perform COF testing. This sled is an optional accessory that may be purchased separately for use with the AR-2000.

Halt Mode Setup
When HALT MODE is set to ON, the motor will automatically stop after 5 minutes of no activity.
- From the Main Screen, tap Setup.
- Select Halt Mode.
- Choose ON or OFF.
- Tap OK to confirm.
Locating Function Switches for Constant Speed Mode
Proper placement of the function switches is essential to ensure that the data recorded represents the central, most consistent portion of the test material. Follow the steps below to position the switches correctly.
- Determine the test method and identify the sled's starting position for the selected procedure.
- Position the HOME switch so that it aligns with the magnet on the back of the sled when the sled is at the starting position.
- Place the START switch at least 1.5 inches to the left of the HOME switch.
- Position the STOP switch far enough to the left of the START switch to ensure the full desired portion of test data is collected.
- Fine-tune the placement of the switches so that the “heart” or central region of the material is captured in the recorded data. A few practice tests using samples of similar size are recommended to verify switch placement.
NOTE: As the test platform moves past the START switch, the display will show “Collecting test data”. The system will continue updating the real-time load value while data collection is active.
Peel Rate Geometry/Discussion
AR-2000 Peel Rate Geometry
- Refer to the diagram below.
- Crosshead Rate = Hypotenuse (this is the speed set on machine control).
- Peel Rate = Load Cell Leg.
- Load cell angle of triangle = θ = 45° (based on 90° peel test).
- Formula to solve for load cell leg of triangle: Peel Rate = Cos (θ) × Crosshead Rate.
- Using a Crosshead Rate of 12 inches/minute: Peel Rate = Cos (θ) × 12, where cos(45°) is 0.707.
- The Peel Rate equals 8.5 inches/minute for a Crosshead Rate of 12 inches/minute.

AR-2000 Peel Rate Discussion
There is a difference in the peel rate with regards to using a 90° fixture on a Tensile machine versus a sled type machine such as the ChemInstruments model AR-2000. If both devices are set to operate at the same speed, the Tensile machine will peel a tape at that same rate, but the AR-2000 will peel a tape slower.
The term Peel Rate describes the separation rate at the peel junction, the point where tape separation from a test panel occurs.
The term Crosshead Rate describes the rate of the mechanism that moves the test panel.
Consider a triangle that makes up the pulling and peeling functions on a Tensile machine. The peel and crosshead rates are equal since the peeling action is performed in the horizontal leg of the triangle and motion occurs in the vertical leg. Since the triangle is a right triangle when performing a 90° peel, the legs are equal and thus so is the Peel Rate with respect to the Crosshead Rate.
Consider a triangle that makes up the pulling and peeling functions on an AR-2000 machine. The peel and crosshead rate are not equal since the peeling action is performed in the load cell leg of the triangle and motion occurs in the hypotenuse. The Peel Rate is therefore a factor of the angle between the load cell leg and the hypotenuse; simple trigonometry applies here. Since the triangle is a right triangle when performing a 90° peel, the load cell leg is shorter than the hypotenuse and thus the Peel Rate is less with respect to the Crosshead Rate. Knowing the 90° angle of peel and using a Crosshead Rate of 12 inches/minute, the math in the above noted example works out to a Peel Rate of 8.5 inches/minute.
Therefore, the general formulas for a sled type machine such as the ChemInstruments AR-2000 are:
Peel Rate = 0.707 × Crosshead Rate
Crosshead Rate = Peel Rate ÷ 0.707
Running a Test
Peel adhesion tests follow standard methods (ASTM, PSTC, TLMI, etc.) and measure how strongly a PSA material sticks to a stainless-steel test panel as it is peeled away.
Use a standard test panel: 2 inch wide and 5 or 6 inch long.
Install the Panel Edge Brackets (90° and 180° Peel)
- Locate the four mounting holes closest to the left end of the test platform.
- Position the panel edge brackets on the platform at these holes.
- Install the four small bolts and tighten securely.
- Verify bracket orientation: the recessed side faces inward (toward the panel), and the closed ends point to the right.
- Slide the test panel in from the left to confirm it moves smoothly into the brackets.
Methods for Testing Short Samples
When test specimens are too short to be properly secured in the instrument grips, extension tabs may be attached to the specimen ends to provide additional gripping length. Proper use of extension tabs helps prevent specimen slippage and reduces the likelihood of grip-induced failures during testing.
Extension tabs should be made from a material that is strong, flexible, and dimensionally stable. The extension tab material should not excessively stretch or deform during the test.
Best extension materials
Polyester film (PET/Mylar); polypropylene film; thin, flexible, low-stretch materials.
Materials to avoid
Stretchy or elastic materials; very thick or stiff materials; heavy materials; aggressive adhesives or uneven splices.
Attachment methods
Double-sided adhesive tape; pressure-sensitive adhesive; mechanical clamping aids. The attachment method should provide a secure bond without affecting the actual test area.
Using improper extension materials can skew test results by changing the peel angle, adding extra resistance, or absorbing force during the test. The extension should remain as mechanically neutral as possible so the tester measures only the adhesive's performance.
180 Degree Tests
Set Up for 180° Peel Test
- Position the test platform horizontally.
- Adjust the load cell assembly to the lowest position on the mast.
- Verify that both the platform and load cell are level and secure.
NOTE: The load cell must be calibrated while positioned at the 180° test angle before running a test.

90 Degree Tests
Set Up for 90° Peel Test
- Loosen the clamping bolt on the rear of the pivot head assembly.
- Slide the bracket up the mast to raise the test platform.
- Retighten the rear clamping bolt to secure the platform.
- Loosen the front clamping bolt on the load cell assembly.
- Tilt the load cell assembly counterclockwise until it locks into the detent position.
- Tighten the front clamping bolt to secure the load cell.
The load cell will now be positioned at a 90° angle to the raised test platform.
NOTE: The load cell must be calibrated while positioned at the 90° test angle before running a test.

Test Angles Between 90 and 180 Degree Tests
Set Up for Test Angles Between 90° and 180°
- Determine the desired test angle required by the test method.
- Divide the desired test angle by 2 to calculate angle A. Angle A is the setting used for both the test platform and the load cell.
- Adjust the test platform and load cell to angle A.
- Run the test following the standard test procedure.
NOTE: The load cell must be calibrated at the correct angle A before performing the test.

Test Procedure: Constant Speed Mode
- Slide the test panel with the test material into the edge brackets with the free end of the test strip to the left.
- Bend the free end of the test strip back and insert it into the grip. (See Grip Operation)
- Set the test platform speed as required. (See Constant Speed Setup)
- Verify the AR-2000 is not in the SETUP screen.
- Turn the clutch handle to the left to disengage the platform from the drive chain.
- Move the test platform (sled) to the start position at the right end of the test bed.
NOTE: The test platform must pass the HOME switch before engaging the drive to ensure proper data collection.
- Confirm the chain is moving. If not, press the START MOTOR button on the main screen.
- Turn the clutch handle clockwise to engage the test platform. When the platform passes the START switch, the display will show “Collecting test data”.
- When the platform passes the STOP switch, the graph screen will appear showing the test graph and the minimum, maximum and average values.
- To run another test, replace the test material and repeat starting at Step 5. No control settings need to be changed if using the same test method.
NOTE: To change force units, select SETUP → UNITS, choose the desired unit of measure, then select OK.
Test Procedure: Ramp Mode
- Slide the test panel with the test material into the edge brackets with the free end of the test strip to the left.
- Bend the free end of the test strip back and insert it into the grip. (See Grip Operation)
- Set the ramp test parameters as required. (See Ramp Speed Setup)
- Verify the AR-2000 is not in the SETUP screen.
- Turn the clutch handle to the left to disengage the platform from the drive chain.
- Move the test platform (sled) to the start position at the right end of the test bed.
- Press the START TEST button.
- Turn the clutch handle clockwise to engage the test platform.
- If a START FORCE greater than 0 grams is set, the platform will move at 5 in/min until the load cell measures the start force.
- The test will then run through all programmed steps at the specified speeds for the set test length.
- When the ramp test is complete, the graph screen will appear showing the test graph and the minimum, maximum and average values.
- To run another test, replace the test material and repeat starting at Step 5. No control settings need to be changed if using the same test method.
NOTE: To change force units, select SETUP → UNITS, choose the desired unit of measure, then select OK.
Test Procedure: COF Mode
- Attach the sample material to both the Test Sled and the Test Platform according to the specified test method.
- Place the Test Sled in the center of the Test Platform, positioned as far left as the connecting cable allows.
- Align the Test Sled so its edges are parallel with the edges of the Test Platform.
- Adjust the sled position so the cable has slack and rests on the platform. The Current Load reading should be below 5 grams.
- Press the START TEST button.
- Turn the clutch handle clockwise to engage the Test Platform.
- Press the STOP TEST button once the Test Sled has traveled the required distance.
- View the Static and Kinetic COF results on the STATISTICS screen.
NOTE: To change force units, select SETUP → UNITS, choose the desired unit of measure, then select OK.
COF Test Description and Results
During a COF test, the Test Platform moves at a constant speed while the Test Sled remains stationary. This movement creates friction between the two surfaces. The force produced by this friction is measured by the load cell and used to calculate the Static COF and Kinetic COF of the test material.
Static COF
The static portion of the test occurs first. The static length is set in the setup screen and can range from 1 to 10 seconds. The highest force measured during this time is saved as the First Peak. The Static COF is calculated using the formula:
Static COF = First Peak (in grams) ÷ Sled Mass (in grams)
Kinetic COF
After the static portion, the test continues into the kinetic portion. All remaining force data points are used to calculate the average, high, and low values. The Kinetic COF is calculated using the formula:
Kinetic COF = Average (in grams) ÷ Sled Mass (in grams)
EZ Data
EZ Data is a proprietary software application developed by ChemInstruments, designed to run on your computer and seamlessly interface with ChemInstruments testing equipment. This powerful tool enables users to:
- Save test data files for archival or further analysis
- Export raw test data directly to Microsoft Excel
- Graph and crop data for clearer visual representation
- Tabulate test data files for easy comparison
- Overlay multiple test results to analyze performance trends
For detailed instructions on software features, setup, and operation, please consult the EZ Data User Manual.
The AR-2000 tester connects to your computer using a USB Type A-to-B cable, compliant with USB 2.0 (Revision 2.0) standards.
EZ Data Main Screen
The images below display the main screen of the EZ Data software with an AR-2000 tester connected. This interface provides a comprehensive overview of the testing process, including:
- Real-time load readings displayed as both a numeric value and a dynamic graph as data is received from the load cell
- Current test setup parameters, clearly shown for reference
This intuitive layout ensures users can monitor, control, and modify tests with efficiency and precision.
EZ Data Setup Screen
Test setup is streamlined within a single, centralized screen in EZ Data, providing a user-friendly interface for configuring all necessary test parameters. This unified setup screen allows users to efficiently define key settings such as test speed, units, and mode specific settings, all without navigating through multiple menus. By consolidating setup functions into one location, EZ Data enhances workflow efficiency and reduces the potential for configuration errors, ensuring consistent and reliable test execution.
Constant Speed Mode


Ramp Speed Mode


COF Mode


Maintenance
Machine Troubleshooting
The troubleshooting chart describes some problems that may occur over time. After determining the problem, follow one of the following maintenance procedures.
| Problem | Possible Cause | Procedure |
|---|---|---|
| No data collected | HOME switch not tripped | Reposition HOME switch |
| START switch too close to HOME or STOP switch | Move START switch at least 1.5 inches away from HOME and STOP switches | |
| Display is in SETUP screen | Go to MAIN screen to run a test | |
| Magnet missing on test platform | Reattach magnet to test platform | |
| Test platform skips | Loose chain | Refer to Chain Adjustment |
| Test platform engaging finger out of adjustment | Refer to Test Platform Engaging Finger | |
| Data measurement consistently low/high | Improper calibration | Check calibration and/or calibration angle |
| Bad calibration | Refer to load cell calibration | |
| Calibration drifts | Bad or damaged load cell | Replace load cell |
| Display is black | Display is bad | Replace display |
| Power switch is not ON | Turn ON power | |
| Power supply is bad | Replace power supply | |
| Display is stuck at ChemInstruments logo | Control board is bad | Replace control board |
Verify Load Cell Hardware
The HARDWARE TOOLS screen is used to check that the load cell, cable, and control board are operating properly. This screen is accessed from the SETUP menu.

Checking the Load Cell
- With no load applied, the Load Cell Reading should be around 32,000.
- When pulling on the load cell, the reading should increase. The harder you pull, the higher the number. The maximum reading is approximately 65,000.
- When pushing on the load cell, the reading should decrease. The harder you push, the lower the number. The minimum reading is approximately 0.
If the readings change as described above, the load cell and hardware are functioning correctly.
Maintenance Procedures
As with any precision equipment it is important to provide care and maintenance to ensure proper performance and long life. The following section will address certain procedures for making changes in the AR-2000 and providing care for proper operation.
Mechanical Maintenance Schedule
The AR-2000 Adhesion/Release tester is a durable and well-designed piece of testing equipment requiring only minimal maintenance. In addition to normal and weekly general cleaning, ChemInstruments recommends that the following additional steps be performed on a monthly basis or as required.
- Check and adjust, as needed, the drive chain.
- Lubricate the drive chain with a chain oil.
- Clean linear rods.
- Check and adjust the engaging finger on the test platform.
- Clean and lubricate the drive & idler shafts and their bronze bearings.
These simple steps, if performed regularly, can ensure the continued reliable performance of your AR-2000 Adhesion/Release tester.
Chain Adjustment
After an extended period of use the chain on the AR-2000's drive will stretch. This can cause undue vibration and improper drive for the test platform. This chain can be easily adjusted by performing the following procedure.
- Make sure the AR-2000 has been turned off and unplugged from the electrical outlet.
- Remove the top guard in order to gain access to the four locking bolts on the bearing slide.
- With a 7/32 Allen wrench loosen the four locking bolts on the bearing slide.
- Locate the adjusting screws on the end plate at the right end of the test bed.
- With a 3/16 Allen wrench, turn each of the adjusting screws ¼ turn.
- Check the tension of the chain before turning the adjusting bolt again. Proper adjustment will allow the chain to flex between sprockets, and engage the test platform without skipping.
- Once adjusted, retighten the four locking bolts described in step 3.
Test Platform Engaging Finger
The engaging finger on the bottom of the test platform must be positioned 90° to the bottom of the test platform in order for it to catch the chain. To adjust the engaging finger, perform the following procedure.
- Make sure the power to the AR-2000 has been disconnected.
- Check the position of the engaging finger by moving the clutch handle to the “engage” position. The engaging finger should be positioned at 90° to the bottom of the test platform.
- To adjust the engaging finger, turn the clutch handle to the 12 o'clock position.
- Using a 3/32" Allen key loosen the setscrew on the engaging finger and rotate it so that it is fully extended downward. Retighten the setscrew.
Test Platform & Linear Rods
The components of the test platform require maintenance to ensure proper performance. Every 3 months, or as needed, the following procedure should be performed.
- Disconnect the power to the AR-2000.
- Remove the top guard to the test bed.
- With a soft clean cloth, wipe the linear rods. These rods provide the surface for the test platform's linear bearings to travel on as tests are conducted.
- Wipe the rods with a light lubricant.
- Lubricate the drive and idler shafts and their bronze bearings with a light lubricant.
Touchscreen Cleaning Guidelines
The touch panel is sensitive to chemicals and requires careful cleaning to maintain optimal functionality and appearance. Follow these specific cleaning instructions to ensure safe and effective care:
- Use a soft, lint-free cloth for cleaning. The 3M Microfiber Lens Cleaning Cloth is highly recommended as it effectively cleans the touch panel without the need for liquid cleaners.
- The cloth may be used dry or lightly dampened with a mild cleaner or ethanol. Ensure the cloth is only lightly damp, never wet.
- Never apply cleaner directly to the touch panel surface. If any liquid accidentally contacts the panel, immediately blot it with an absorbent cloth to prevent seepage.
- Use only neutral pH cleaners (neither acidic nor alkaline). Avoid any cleaners containing ammonia, phosphates, or ethylene glycol.
- When applying cleaner, avoid contact with the edges of the film or glass and the flex cable tail to prevent damage.
- Clean the surface gently, following the direction of any surface texture if present.
- Do not use harsh chemicals such as paint thinner, acetone, toluene, xylene, kerosene, or strong alcohols like propyl or isopropyl alcohol in high concentrations.
- Suitable cleaning products are commercially available and specifically formulated for delicate touch panels. Examples include Klear Screen™ and retail brands like Glass Plus® Glass and Surface Cleaner by Reckitt Benckiser.
- Most commercial products contain 1–3% isopropyl alcohol by volume, which is generally safe for use on resistive touch panels.
IMPORTANT: Always check the product's ingredient list carefully. Many cleaners contain unacceptable substances such as ammonia, phosphates, or ethylene glycol, which can damage the touch panel's optical clarity and functionality.